[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118669,789,1,"单选题","在某工程网络计划中，工作M的最早开始时间为第7天，其持续时间为5d。工作M工段有三项紧后工作，它们的最早开始时间分别为第15天、第16天和第18天，则工作M的自由时差为()d。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","8",{"key":23,"text":24,"correct":18},"D","10","2021\u002F2020教材P141页 自由时差公式，工作自由时差=紧后工作的最早开始时间—本工作的最早开始时间-本工作的持续时间，15-7-5=3天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]