[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118668,789,1,"单选题","关于关键工作和关键线路，下列说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路上的工作全部是关键工作",true,{"key":16,"text":17,"correct":18},"B","关键工作不能在非关键线路上",false,{"key":20,"text":21,"correct":18},"C","关键线路上不允许出现虚工作",{"key":23,"text":24,"correct":18},"D","关键线路上的工作总时差均为零","2021\u002F2020教材P141页 自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。网络图上的关键线路可用双线或粗线标注。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]