[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118667,789,1,"单选题","下列网络计划的计算工期是（）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":14},"C","12",{"key":22,"text":23,"correct":24},"D","14",true,"2021\u002F2020教材P141页 自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。持续时间最长的线路为ACE，时间为14天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]