[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118666,789,1,"单选题","某双代号网络计划如图所示（时间单位：d），则该计划的关键线路是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→④→⑤→⑥→⑦",true,{"key":16,"text":17,"correct":18},"B","①→②→④→⑤→⑦",false,{"key":20,"text":21,"correct":18},"C","①→③→④→⑤→⑥→⑦",{"key":23,"text":24,"correct":18},"D","①→③→④→⑤→⑦","2021\u002F2020教材P141页 自始至终全部由关键工作组成的线路为关键线路，或线路上总的工作持续时间最长的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]