[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118665,789,1,"单选题","某工程网络计划中，工作W的最早开始时间和最迟开始时间分别为第12天和第15天，其持续时间为5天，工作W有3个紧后工作，它们的最早开始时间分别为第21天，24天和第28天，W的自由时差为（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","11","2021\u002F2020教材P141页 持续时间为5天，已知工作W最早开始时间为第12天，所以，W的最早完成时间为12+5=17天，自由时差为紧后工作最早开始时间的最小值减去本工作的最早完成时间，所以W的自由时差=21-17=4天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]