[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118664,789,1,"单选题","在双代号或单代号网络计划中，判别关键工作的条件是该工作（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差最小",false,{"key":16,"text":17,"correct":14},"B","与其紧后工作之间的时间间隔为零",{"key":19,"text":20,"correct":14},"C","持续时间最长",{"key":22,"text":23,"correct":24},"D","最迟开始时间与最早开始时间的差值最小",true,"2021\u002F2020教材P141页 4.关键工作和关键线路的确定(1)关键工作网络计划中总时差最小的工作是关键工作。总时差等于本工作最迟完成时间减去最早完成时间；或者等于本工作最迟开始时间减去最早开始时间，故D项表达的就是总时差最小的工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]