[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118662,789,1,"单选题","下列网络计划中，工作E的最迟开始时间是第()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","7","2021\u002F2020教材P140页 最迟开始时间等于最迟完成时间减去持续时间。工作E的最迟完成时间为9，则其最迟开始时间为6。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]