[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118661":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118661,789,1,"单选题","已知某网络计划中工作M的自由时差为3天，总时差为5天。通过检查分析，发现该工作的实际进度拖后，且影响总工期1天。在其他工作均正常的前提下，工作M的实际进度拖后()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","6",true,{"key":23,"text":24,"correct":14},"D","9","2021\u002F2020教材P140页 总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间，可知在其他工作均正常进行的前提下，由于M工作有5天总时差。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]