[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118659,789,1,"单选题","某工程网络计划共有十项工作，其中A工作为起始工作，其紧后工作为 B，B工作的紧后工作为 C，持续时间分别为3d、4d、4d，B工作的总时差为2d，则B工作的最迟开始时间为()d。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","7","2021\u002F2020教材P140页 计算工作总时差总时差等于其最迟开始时间减去最早开始时间，或等于最迟完成时间减去最早完成时间，即最迟开始时间等于最早开始时间+总时差B为A的紧后工作，A的持续时间为3天，则B的最早开始时间为3天，则最迟开始时间=3+2=5天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]