[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118658,789,1,"单选题","已知工程网络计划中，工作M、N、P无紧后工作，则该网络计划的计算工期应等于这三项工作的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早完成时间的最大值",true,{"key":16,"text":17,"correct":18},"B","最迟完成时间的最大值",false,{"key":20,"text":21,"correct":18},"C","最早完成时间的最小值",{"key":23,"text":24,"correct":18},"D","最迟完成时间的最小值","2021\u002F2020教材P140页 计算工期等于以网络计划的终点节点为箭头节点的各个工作的最早完成时间的最大值。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]