[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118657,789,1,"单选题","在计算双代号网络计划的时间参数时，工作的最迟完成时间等于其所有紧后工作的（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最早开始时间的最小值",false,{"key":16,"text":17,"correct":14},"B","最早开始时间的最大值",{"key":19,"text":20,"correct":21},"C","最迟开始时间的最小值",true,{"key":23,"text":24,"correct":14},"D","最迟开始时间的最大值","2021\u002F2020教材P140页 工作最迟时间参数受到紧后工作的约束，故其计算顺序应从终点节点起，逆着箭线方向依次逐项计算。最迟完成时间等于各紧后工作的最迟开始时间的最小值。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]