[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118655,789,1,"单选题","双代号网络计划如下图所示(时间单位:天),其计算工期是()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":18},"B","17",true,{"key":20,"text":21,"correct":14},"C","18",{"key":23,"text":24,"correct":14},"D","20","2021\u002F2020教材P140页 由图可知关键线路为1-3-5-7和1-3-4-6-7,计算工期为17天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]