[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118653,789,1,"单选题","在双代号网络计划中，如果其计划工期与计算工期相等，且工作i-j的完成节点在关键线路上，则工作i-j的自由时差（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","等于零",false,{"key":16,"text":17,"correct":14},"B","小于零",{"key":19,"text":20,"correct":14},"C","小于其相应的总时差",{"key":22,"text":23,"correct":24},"D","等于其相应的总时差",true,"2021\u002F2020教材P139页 由于工作i-j的完成节点在关键线路上，说明该节点j为关键节点，即工作i-j的紧后工作中必有关键工作，此时工作i-j的自由时差就等于其总时差。故选D。 计算工期=计划工期，只能代表总时差为0的工作为关键工作，而该题完成结点在关键线路上，所以总时差=本工作的自由时差+紧后工作的总时差最小值(即将为0)，所以总时差=自由时差",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]