[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118651,789,1,"单选题","已知工作A的紧后工作是B和 C，工作B的最迟开始时间为14天，最早开始时间为10天，工作C的最迟完成时间为16天，最早完成时间为14天，工作A的自由时差为5天，则工作A的总时差为（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","11","2021\u002F2020教材P139页 已知B的总时差=最迟开始时间-最早开始时间=14-10=4天，C的总时差=16-14=2天，A的总时差=自由时差+紧后工作的最小总时差。 依题意，A的总时差=5+2=7",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]