[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118649,789,1,"单选题","已知下列双代号网络图，由于设计图纸的变更，造成D工作延误6天，则总工期将延长（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","2021\u002F2020教材P139页 本题关键线路为1——2——3——4——5——6，总工期为17天（8+4+5=17天），而D工作所在的线路最大长度为15天（线路1——2——5——6，8+2+5=15天）。因此，D工作有2天的总时差，如果工作D拖延6天开始，则总工期将延长4天（6-2=4天）。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]