[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118648,789,1,"单选题","已知某工程双代号网络图如下，按照计划安排F工作的最早开始时间为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第10天",false,{"key":16,"text":17,"correct":18},"B","第12天",true,{"key":20,"text":21,"correct":14},"C","第14天",{"key":23,"text":24,"correct":14},"D","第17天","2021\u002F2020教材P139页 F工作开始前，需要先完成工作A、工作D和工作C。完成工作A、工作D的总时间为10天（8+2天）；完成工作A、工作C的总时间为12天（8+4天）。两者取大，为12天。因此，F工作最早开始时间为12天，选项B正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]