[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118647,789,1,"单选题","工作()等于该工作最早开始时间加上其持续时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟开始时间",false,{"key":16,"text":17,"correct":18},"B","最早完成时间",true,{"key":20,"text":21,"correct":14},"C","最早结束时间",{"key":23,"text":24,"correct":14},"D","最迟结束时间","2021\u002F2020教材P139页 最早完成时间等于最早开始时间加上其持续时间",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]