[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118646,789,1,"单选题","最迟完成时间是指（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在各项紧前的工作全部完成后，工作有可能开始的最早时刻",false,{"key":16,"text":17,"correct":14},"B","在各项紧前的工作全部完成后，工作有可能完成的最早时刻",{"key":19,"text":20,"correct":14},"C","在不影响整个任务按期完成的前提下，工作必须开始的最迟时刻",{"key":22,"text":23,"correct":24},"D","在不影响整个任务按期完成的前提下，工作必须完成的最迟时刻",true,"2021\u002F2020教材P139页 最迟完成时间，是指在不影响整个任务按期完成的前提下，工作必须完成的最迟时刻。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]