[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118645,789,1,"单选题","已知在双代号网络计划中，某工作有2项紧后工作，它们的最迟开始时间分别为11天和13天。如果该工作的持续时间为3天，则该工作最迟开始时间为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8天",true,{"key":16,"text":17,"correct":18},"B","10天",false,{"key":20,"text":21,"correct":18},"C","11天",{"key":23,"text":24,"correct":18},"D","13天","2021\u002F2020教材P139页 最迟开始时间是指在不影响整个任务按期完成的前提下，工作必须开始的最迟时刻。2项紧后工作的最迟开始时间分别为11天和13天，则本工作的最迟结束时间为11天，该工作的持续时间为3天，则该工作最迟开始时间为8天",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]