[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118644,789,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作B的总时差和自由时差()周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为1",false,{"key":16,"text":17,"correct":18},"B","分别为2和1",true,{"key":20,"text":21,"correct":14},"C","分别为4和1",{"key":23,"text":24,"correct":14},"D","均为4","2021\u002F2020教材P139页 总时差是指在不影响总工期的前提下，工作可以利用的机动时间。自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间。工作B紧后工作最早开始时间为4周，B最早结束时间为3周，所以B的自由时差为1周。总时差为B工作的自由时差+J工作的自由时差为2周。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]