[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118643,789,1,"单选题","在工程网络计划的执行过程中，监理工程师检查实际进度时，只发现工作M的总时差由原计划的3天变为-2天，说明工作M的实际进度()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖后5天，影响工期2天",true,{"key":16,"text":17,"correct":18},"B","拖后2天，影响工期2天",false,{"key":20,"text":21,"correct":18},"C","拖后3天，影响工期2天",{"key":23,"text":24,"correct":18},"D","拖后2天，影响工期1天","2021\u002F2020教材P139页 总时差是指在不影响总工期的前提下，工作可以利用的机动时间。原来的总时差是3天，现在变成了-2天，也就是把原来的3天总时差用了还不够，又增加了2天，即拖后了5天，而M工作有3天总时差，所以工期影响了2天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]