[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118642,789,1,"单选题","某工程网络计划中，工作P的最迟完成时间为第25天，其持续时间为6天。该工作有三项紧前工作，它们的最早完成时间分别为第10天、第12天和第13天，则该工作P的总时差为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6天",true,{"key":16,"text":17,"correct":18},"B","10天",false,{"key":20,"text":21,"correct":18},"C","12天",{"key":23,"text":24,"correct":18},"D","14天","2021\u002F2020教材P139页 工作P的最早开始时间=max(10，12，13)=13，最早完成=13+6=19，总时差=最迟完成-最早完成=25-19=6。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]