[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118639,789,1,"单选题","某工程网络计划中工作M的总时差为3d，自由时差为0。该计划执行过程中，只有工作M的实际进度拖后4d，则工作M的实际进度将其紧后工作的最早开始时间推迟和使总工期延长的时间分别为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3d和0d",false,{"key":16,"text":17,"correct":14},"B","3d和1d",{"key":19,"text":20,"correct":14},"C","4d和0d",{"key":22,"text":23,"correct":24},"D","4d和1d",true,"2021\u002F2020教材P139页 总时差，是指在不影响总工期的前提下可以利用的机动时间。自由时差，是指在不影响其紧后工作最早开始的前提下可以利用的机动时间。则工作M的实际进度将其紧后工作的最早开始时间推迟为：自由时差0-实际拖延4=4d，使总工期延长的时间为：总时差3-实际拖延4=1d。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]