[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118638,789,1,"单选题","某工程施工网络计划经监理工程师批准后实施。已知工作A有5天的自由时差和8天的总时差，由于第三方原因，使工作A的实际完成时间比原计划延长了12天。在无其它干扰的情况下，其紧后工作的最早开始时间将推迟()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":24,"correct":14},"D","12","2021\u002F2020教材P139页 自由时差是指在不影响其紧后工作最早开始时间的前提下，本工作可以利用的机动时间。本例中其紧后工作的最早开始时间推迟天数=12-5=7天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]