[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118636,789,1,"单选题","某网络计划中，工作M的最早完成时间是第8天，最迟完成是第13天，工作的持续时间为4天，与所有的紧后工作的间隔时间最小值为2天，则该工作的自由时差为()天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","5","2021\u002F2020教材P139页 自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间。自由时差等于时间间隔的最小值。在本题中为2天。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]