[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118635,789,1,"单选题","在工程网络计划执行过程中，如果某项工作实际进度拖延的时间没有超过其自由时差，则()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不影响其紧后工作的最早开始",true,{"key":16,"text":17,"correct":18},"B","影响其紧后工作的最早开始时间",false,{"key":20,"text":21,"correct":18},"C","该工作的总时差不会变",{"key":23,"text":24,"correct":18},"D","可能会影响工程总工期","2021\u002F2020教材P139页 自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间。某项工作实际进度拖延的时间超过了自由时差，即表示影响了其紧后工作的最早开始时间。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]