[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118634,789,1,"单选题","单代号网络计划中，工作的自由时差和该工作与其紧后工作之间的时间间隔的关系是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","自由时差就等于时间间隔",false,{"key":16,"text":17,"correct":14},"B","自由时差与时间间隔无直接关系",{"key":19,"text":20,"correct":14},"C","自由时差等于该工作与其紧后工作之间的时间间隔的最大值",{"key":22,"text":23,"correct":24},"D","自由时差等于该工作与其紧后工作之间的时间间隔的最小值",true,"2021\u002F2020教材P139页 自由时差是指在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]