[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118631,789,1,"单选题","在某工程单代号网络计划中，说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路只有一条",true,{"key":16,"text":17,"correct":18},"B","在计划实施过程中，关键线路可以改变",false,{"key":20,"text":21,"correct":18},"C","关键工作的机动时间最少",{"key":23,"text":24,"correct":18},"D","相邻关键工作之问的时间间隔为零","2021\u002F2020教材P137页 在各条线路中，有一条或几条线路的总时间最长，称为关键路线，一般用双线或粗线标注。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]