[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118630,789,1,"单选题","下列属于双代号网络计划中工作之间的逻辑关系的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工艺关系",true,{"key":16,"text":17,"correct":18},"B","流程关系",false,{"key":20,"text":21,"correct":18},"C","紧前紧后关系",{"key":23,"text":24,"correct":18},"D","并列关系","2021\u002F2020教材P137页 网络图中工作之间相互制约或相互依赖的关系称为逻辑关系，它包括工艺关系和组织关系，在网络中均应表现为工作之间的先后顺序。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]