[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118626,789,1,"单选题","下列关于双代号网络计划绘图规则的说法，错误的有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","网络图必须正确表达各工作间的逻辑关系",false,{"key":16,"text":17,"correct":18},"B","网络图中可以出现循环回路",true,{"key":20,"text":21,"correct":14},"C","单目标网络计划只有一个起点节点和一个终点节点",{"key":23,"text":24,"correct":14},"D","网络图中严禁出现没有箭头节点或没有箭尾节点的箭线","2021\u002F2020教材P138页 2)双代号网络图中，严禁出现循环回路。所谓循环回路是指从网络图中的某一个节点出发，顺着箭线方向又回到了原来出发点的线路。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]