[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118625,789,1,"单选题","节点是双代号网络计划中箭线之间的连接点，每一个双代号网络图有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一个起点节点和一个终点节点",true,{"key":16,"text":17,"correct":18},"B","一个起点节点和多个终点节点",false,{"key":20,"text":21,"correct":18},"C","多个起点节点和一个终点节点",{"key":23,"text":24,"correct":18},"D","多个起点节点和多个终点节点","2021\u002F2020教材P138页 （二）根据双代号网络计划图的绘制规则（7）、双代号网络图中应只有有一个起点节点和一个终点节点（多目标网路计划除外），而其他所有节点均应是中间节点。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]