[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118624,789,1,"单选题","根据下表给定的逻辑关系绘制某分部工程双代号网络计划如下图所示，其作图错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","节点编号不对",false,{"key":16,"text":17,"correct":18},"B","有多个终点节点",true,{"key":20,"text":21,"correct":14},"C","有多个起点节点",{"key":23,"text":24,"correct":14},"D","逻辑关系不对","2021\u002F2020教材P138页 （7）双代号网络图中应只有一个起点节点和一个终点节点（多目标网络计划除外），而其他所有节点均应是中间节点。此图出现2个终点节点即节点8和9。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]