[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118623,789,1,"单选题","双代号网络计划中关于节点的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一个开始节点和一个结束节点",true,{"key":16,"text":17,"correct":18},"B","一个开始节点和多个结束节点",false,{"key":20,"text":21,"correct":18},"C","多个开始节点和一个结束节点",{"key":23,"text":24,"correct":18},"D","多个开始节点和多个结束节点","2021\u002F2020教材P138页 (7)双代号网络图中应只有一个起点节点和一个终点节点（多目标网络计划除外），而其他所有节点均应是中间节点。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]