[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118620,789,1,"单选题","关于双代号网络图绘图规则的说法,正确是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","箭线不能交叉",false,{"key":16,"text":17,"correct":14},"B","关键工作必须安排在图面中心",{"key":19,"text":20,"correct":21},"C","只有一个起点节点",true,{"key":23,"text":24,"correct":14},"D","工作箭线只能用水平线","2021\u002F2020教材P138页 (6)绘制网络图时，箭线不宜交叉，当交叉不可避免时，可用过桥法或指向法。(7)双代号网络圈中应只有一个起点节点和一个终点节点（多目标网络计划除外），而其他所有节点均应是中问节点、(8)双代号同络圈应条理清楚，布局合理．饲如，网络图中的工作箭线不宜画成任意方向或曲线形状，尽可能用水平线或斜线；关键线路、关健工作安拍在图面中心位置，其他工作分散在两边；避免倒回箭头等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]