[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118616,789,1,"单选题","横道图进度计划的优点是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","表达方式直观",true,{"key":16,"text":17,"correct":18},"B","工作时差易于分析",false,{"key":20,"text":21,"correct":18},"C","便于确定关键工作",{"key":23,"text":24,"correct":18},"D","工作之间的逻辑关系表达清楚","2021\u002F2020教材P134页 横道图计划表中的进度线（横道与时间坐标相对应，这种表达方式较直观，易看懂计划编制的意图。但是，横道图进度计划法也存在一些问题，如：(1)工序（工作之间的逻辑关系可以设法表达，但不易表达清楚；(2)适用于手工编制计划；(3)没有通过严谨的进度计划时间参数计算，不能确定计划的关键工作、关键路线与时差(4)计划调整只能用手工方式进行，其工作量较大;(5)难以适应较大的进度计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]