[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118613,789,1,"单选题","下列关于横道图计划法的缺点，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","横道图无法表达出工作间的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","关键工作和关键路线可以设法表达，但不易表达清楚",{"key":19,"text":20,"correct":21},"C","计划调整只能用手工方式进行，其工作量时较大",true,{"key":23,"text":24,"correct":14},"D","横道图计划难以适用于中小型进度计划系统","2021\u002F2020教材P134页 道图进度计划法也存在一些问题，如：(1)工序（工作）之间的逻辑关系可以设法表达，但不易表达清楚；(2)适用于手工编制计划；(3)没有通过严谨的进度计划时间参数计算，不能确定计划的关键工作、关键路线与时差；(4)计划调整只能用手工方式进行，其工作量较大；(5)难以适应大的进度计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]