[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118612,789,1,"单选题","下列关于横道图进度计划的表述中，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图是一种最简单、运用最广泛的进度计划方法",false,{"key":16,"text":17,"correct":14},"B","横道图的表头为工作及其简要说明，工作进展表现在时间表格上",{"key":19,"text":20,"correct":14},"C","横道图也可将工作简要说明直接放在横道线条上",{"key":22,"text":23,"correct":24},"D","横道图主要运用于大中型建设项目的进度管理",true,"2021\u002F2020教材P133页 横道图用于小型项目或大型项目子项目上，或用于计算资源需要量、概要预示进度，也可用于其他计划技术的表示结果",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]