[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118611,789,1,"单选题","施工进度计划的编制方法有多种，其中（）是一种最简单并运用最广泛的传统的计划方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":18},"B","双代号网络计划",false,{"key":20,"text":21,"correct":18},"C","单代号网络计划",{"key":23,"text":24,"correct":18},"D","双代号时标网络计划","2021\u002F2020教材P133页 2Z103031横道图进度计划的编制方法横道图是一种最简单并运用最广的传统的计划方法，尽管有许多新的计划技术，横道图在建设领域中的应用还是非常普遍。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]