[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118610,789,1,"单选题","双代号网络图中虚箭线表示()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资源消耗程度",false,{"key":16,"text":17,"correct":14},"B","工作的持续时间",{"key":19,"text":20,"correct":21},"C","工作之间的逻辑关系",true,{"key":23,"text":24,"correct":14},"D","非关键工作","2021\u002F2020教材P135页 在双代号网络图中，为了正确地表达图中工作之间的逻辑关系，往往需要应用虚箭线。虚箭线是实际工作中并不存在的一项虚设工作，故它们既不占用时间，也不消耗资源，一般起着工作之间的联系、区分和断路三个作用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]