[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118607,789,1,"单选题","在双代号网络图中，任意一条实箭线除特殊情况外都()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","只占用时间，不占用资源",false,{"key":16,"text":17,"correct":14},"B","只占用资源，不占用时间",{"key":19,"text":20,"correct":14},"C","既不占用时间，也不占用资源",{"key":22,"text":23,"correct":24},"D","占用时间、消耗资源",true,"2021\u002F2020教材P135页 在双代号网络图中，任意一条实箭线都要占用时间、消耗资源（有时，只占时间，不消耗资源，如混凝土养护）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]