[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118606,789,1,"单选题","关于工程网络计划中虚工作的说法，错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","虚工作表示工作之间的逻辑关系",false,{"key":16,"text":17,"correct":18},"B","虚工作的总时差和自由时差均为零",true,{"key":20,"text":21,"correct":14},"C","虚工作的持续时间为0",{"key":23,"text":24,"correct":14},"D","在双代号网络计划中存在虚工作","2021\u002F2020教材P135页 虚箭线是实际工作中并不存在的一项虚设工作，故它们既不占用时间，也不消耗资源，但是自由时差和总时差并不一定为0，只是持续时间为0",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]