[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118605,789,1,"单选题","虚箭线是实际工作中并不存在的一项虚设工作，故它们（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","既不占用时间，也不消耗资源",true,{"key":16,"text":17,"correct":18},"B","只占时间，不消耗资源",false,{"key":20,"text":21,"correct":18},"C","不占时间，只消耗资源",{"key":23,"text":24,"correct":18},"D","既占时间，又消耗资源","2021\u002F2020教材P135页 虚箭线是实际工作中并不存在的一项虚设工作，故它们既不占时间，也不消耗资源，一般起着工作之间的联系、区分和断路三个作用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]