[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118599,789,1,"单选题","建设工程进度网络计划与横道计划相比，其主要优点是能够()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","明确表达各项工作之间的逻辑关系",true,{"key":16,"text":17,"correct":18},"B","直观表达工程进度计划的计算工期",false,{"key":20,"text":21,"correct":18},"C","明确表达各项工作之间的搭接时间",{"key":23,"text":24,"correct":18},"D","直观表示各项工作的持续时间","2021\u002F2020教材P134页 建设工程进度网络计划横道图相比，最大的优点在于横道图：工序（工作) 之间的逻辑关系可以设法表达，但不易表达清楚，而网络图可以。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]