[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118598,789,1,"单选题","与工程网络计划方法相比，横道图进度计划方法的缺点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","无法确定计划中的关键工作和时差",true,{"key":16,"text":17,"correct":18},"B","不能手动方式改动调整进度计划",false,{"key":20,"text":21,"correct":18},"C","难以直观反映计划所需要的资源数量",{"key":23,"text":24,"correct":18},"D","不可以直观计算计划中工作的时间参数","2021\u002F2020教材P134页 横道图进度计划的缺点有：工序（工作）之间的逻辑关系可以设法表达，但不易表达清楚；适用于手工编制计划；没有通过严谨的进度计划时间参数计算，不能确定计划的关键工作、关键线路与时差；计划调整只能用手工方式进行，其工作量较大；难以适应大的进度计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]