[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118597":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118597,789,1,"单选题","关于横道图计划法的表述，不正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图用于小型项目或大型项目子项目上",false,{"key":16,"text":17,"correct":14},"B","按照所表示工作的详细程度，时间单位可以为小时(h)、天(d)、周",{"key":19,"text":20,"correct":14},"C","横道图计划表中的进度线（横道）与时间坐标相对应，这种表达方式较直观，易看懂计划编制的意图",{"key":22,"text":23,"correct":24},"D","适应大的进度计划系统",true,"2021\u002F2020教材P134页 施工进度计划的编制方法（横道图）原文如下：横道图进度计划法也存在一些问题，如：1、工序（工作）之间逻辑关系可以设法表达，但不易表达清楚；2、适于手工编织；3、不能确定关键路线、关键工作机总时差；4、只能手工进行，工作量大；5、难以适应大的计划系统。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]