[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118591,789,1,"单选题","某双代号网络计划如下图所示。由于业主方要求图纸修改，工作K施工时间共25天，则会影响工期（）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","10","2021\u002F2020教材P135页 双代号相关的内容。 经分析，该双代号网络计划关键线路为30-50-60-70-80，总工期为80天。K工作的总时差为10，所以延误工期25-10-10=5天. @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]