[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118589,789,1,"单选题","双代号网络计划的网络图中，虚箭线的作用是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","正确表达两个工作的间隔时间",false,{"key":16,"text":17,"correct":14},"B","正确表达相关工作的持续时间",{"key":19,"text":20,"correct":14},"C","正确表达相关工作的自由时差",{"key":22,"text":23,"correct":24},"D","正确表达相关工作的逻辑关系",true,"2021\u002F2020教材P135页 在双代号网络图中，为了正确地表达图中工作之间的逻辑关系往往需要应用虚箭线",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]