[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118585,789,1,"单选题","施工企业的施工生产计划根据施工任务量、企业经营的需求和资源利用的可能性等，合理安排计划周期内的施工生产活动，它包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单体工程施工进度计划",false,{"key":16,"text":17,"correct":18},"B","企业月度生产计划",true,{"key":20,"text":21,"correct":14},"C","施工总进度规划",{"key":23,"text":24,"correct":14},"D","施工总进度方案","2021\u002F2020教材P131页 包括年度生产计划，季度生产计划 ，月度生产计划和旬生产计划",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]