[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118584,789,1,"单选题","下列属于施工企业的施工生产计划的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工总进度计划",false,{"key":16,"text":17,"correct":18},"B","月度生产计划",true,{"key":20,"text":21,"correct":14},"C","项目施工的季度施工计划",{"key":23,"text":24,"correct":14},"D","单体工程施工进度计划","2021\u002F2020教材P131页 与施工进度有关的计划如下图所示。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]