[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118581,789,1,"单选题","施工企业的施工生产计划与建设工程项目施工进度计划属于（）的计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一个系统内的同一个层次",false,{"key":16,"text":17,"correct":18},"B","二个不同的系统，但紧密相关",true,{"key":20,"text":21,"correct":14},"C","同一个层次上二种不同系统",{"key":23,"text":24,"correct":14},"D","二个不同系统，毫不相关","2021\u002F2020教材P131页 施工企业的施工生产计划与建设工程项目施工进度计划虽属两个不同系统的计划，但是，两者是紧密相关的。前者针对整个企业，而后者则针对一个具体工程项目，计划的编制有一个自下而上和自上而下的往复多次的协调过程。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]